Shamrock Log Home Construction Day 15 - 33

Day 15

September 22nd, Wednesday

Day 15 – Crew making good progress, stacking logs. Trash Dumpster delivered and job site cleaned.

DSC01379__2__op_640x270.jpg
Day 15
DSC01380__2__op_640x270.jpg
Day 15
DSC01378__2__op_640x270.jpg
Day 15
DSC01381__2__op_640x270.jpg
Day 15

Day 16

September 23rd, Thursday

Day 16 – Crew close to having log wall stack complete. Well contractor onsite, drilled approximately 170 feet deep and installed 1.5 hp pump with the tank.

DSC01386__2__op_640x270.jpg
Day 16
DSC01387__2__op_640x382.jpg
Day 16
DSC01388__2__op_640x270.jpg
Day 16
Image5_op_640x215.jpg
Day 16
Image001__2__op_640x182.jpg
Day 16

Day 17

September 24th, Friday

Day 17 – Crew continues log wall stack, installs decking on 12ft back covered porch. Built temporary stairs. Received interior framing package. Electric company onsite set transformer and energized temporary electric pole.

Day 17

Day 18

September 25th, Saturday

Day 18 – Crew continues working on log stack.

Day 18

Day 19-21

September 26th, Sunday
Day 19 – No Work

September 27th, Monday
Day 20 – Rained out.

September 28th, Tuesday
Day 21 – Log walls complete, Interior Framing 50%.

Day 21
Day 21

Day 22-23

September 29th, Wednesday
Day 22 – Worked 1/2 day due to rain. Crew continues working on framing and starts roof support post.

September 30th, Thursday
Day 23 – Crew works on Structural Open Beam Roof System

Day 23
Day 23
DSC01404__2__op_640x270.jpg
Day 23

Day 24-25

October 1st, Friday
Day 24 – Crew working on open beam roof system.

October 2nd, Saturday
Day 25 – Crew installed all rafters on Structural Open Beam Roof System

Day 25

Day 26-28

October 3rd, Sunday
Day 26 – No work.

October 4th, Monday
Day 27 – Crew working on full log gables ends.

October 5th, Tuesday
Day 28 – Crew finished full log gables.

Day 28
Day 28
Day 28

Day 29

October 6th, Wednesday

Day 29 – Crew begins installing T&G roof covering. Electrician onsite coordinating wiring drops for ceiling areas and scheduled to be onsite to install on Monday.

Day 29
Day 29

Day 30

October 7th, Thursday

Day 30 – Crew finishes installing T&G roof covering.

Day 30

Day 31

October 8th, Friday

Day 31 – Crew working on installing open beam roof purlin system.

Day 31
Day 31

Day 32-33

October 9th, Saturday

Day 32 – Crew finishing open beam roof purlin system and working on open beam covered porches.

October 10th, Sunday – Day 33 – No work.

Day 32