Shamrock Log Home Construction Day 34 - 49

Day 34

October 11th, Monday

Day 34 – Electricians onsite met with the Owner’s and laid out all electric and installed all ceiling drops with wiring rough. Exterior metal clad windows and doors delivered. Crew installing insulation, roof decking

DSC01418__3__op_640x270.jpg
Day 34
DSC01419__2__op_640x270.jpg
Day 34
DSC01420__2__op_640x270.jpg
Day 34
DSC01421__2__op_640x270.jpg
Day 34

Day 35

October 12th, Tuesday

Day 35 – Crew installing insulation, roof decking and working on porches. Building Dept. on site today and signed off on sheathing inspection.

DSC01425__2__op_640x393.jpg
Day 35
DSC01428__2__op_640x270.jpg
Day 35

Day 36

October 13th, Wednesday

Day 36 – Crew working on porches.

DSC01427__2__op_640x297.jpg
Day 36
DSC01426__2__op_640x270.jpg
Day 36

Day 37

October 14th, Thursday

Day 37 – Crew working on porches and installing roof underlayment

DSC01436__2__op_640x241.jpg
Day 37

Day 38

October 15th, Friday

Day 38 – Crew working on interior wall framing. Plumbers onsite working on rough in.

DSC01437__2__op_640x241.jpg
Day 38

Day 39-40

October 16th, Saturday

Day 39 – Crew working on interior wall framing. Plumbers onsite working on rough in.

Day 40 – October 17th, 2010 Sunday – No Work

Day 39

Day 41

October 18th, Monday
Day 41 – Crew working on window and door bucking and front covered porch system. Plumber onsite working on rough in.

Day 41

Day 42

October 19th, Tuesday

Day 42 – Crew working on window bucking and bay window. Plumbers onsite working on rough-in. Electricians onsite working on rough-in. Hardwood and tile subcontractor onsite measuring layout for finish floors and shower hops.

Day 42

Day 43

October 20st, Wednesday

Day 43 – Crew installing windows. Framing bay window. Plumbers onsite working on rough-in and installing waterline to well.

Day 43
Day 43
Day 43

Day 44-46

October 21th, Thursday
Day 44 – Crew framing 6/0 x 6/10 doors. Completing log to roof transition. Framing bay window.

October 22nd, Friday
Day 45 – Crew working on misc. items, HVAC crew onsite, met with the owner and laid out all vents/returns and installed ductwork.

October 23rd, Saturday
Day 46 – Crew working on misc. items

Day 45
Day 45
Day 46

Day 47-48

October 24th, Sunday

Day 47 – No Work

October 25th, Monday
Day 48 – Crew working on misc. items, drop ceilings, elect. cutouts, finished sheathing bay window and set both 6/0 x 6/10 exterior doors. H.V.A.C crew onsite, met with owner and laid out last 2 vents that were in conflict with floor structural members. “H.V.A.C rough-in complete.” Plumbers onsite, set tub and finishing rough-in. Metal roof contractor onsite taking finish roof measurements and ordered metal to be delivered tomorrow. Coordinated and completed all roof penetrations with roofing contractor (H.V.A.C, Plumbing, and Gas) Metal roof installation scheduled to start Wednesday.

Day 48

Day 49

October 26th, Tuesday

Day 49 – Crew working on misc. items and framing fireplace. ” Plumbers onsite, finishing rough-in. Metal roofing delivered. Meeting onsite with owners to discuss porch rails and picket design.